H2V Marseille - Fos

Pre-FID✓ Source-checked

H2V + Hy2gen (JV); partners: Technip Energies, Hy24, VINCI Airports, Marseille Provence Airport

Project Overview

Country
France
Region
Provence-Alpes-Côte d'Azur
Capacity
390 MW
Technology
Other
Investment · scope not declared (EUR)
€1.5B

≈ $1.6B, converted at EUR_TO_USD = 1.08, fixed on 1 Jun 2026

Subsidy Status
—

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

Announced—
FID—
Construction—
Operational2030planned date

Readiness Score

0/ 100
Early Stage

Weighted checklist of public info. Not a prediction of success.

Development

✗Final Investment Decision+15
✗EPC Contract signed+10
✗Permits obtained+8
✗Grid connection secured+7

Commercial

✗Binding offtake agreement+15
✗MOU / offtake letter of intent+5
✗Confirmed price / tariff+5
✗Applied to government program+5

Financing

✗Project finance / debt secured+10
–Subsidy (not recorded)+0

Track Record

✗Developer has completed H2 project+5
✗Developer has completed RE project+3
✗Developer has energy experience+2