ITM Power / Linde Leuna Green Hydrogen

Operational✓ Source-checked

Linde GmbH (operator/owner) — supplier: ITM Power via ITM Linde Electrolysis GmbH JV

Project Overview

Country
Germany
Region
Saxony-Anhalt
Capacity
24 MW
Technology
PEM Electrolysis
Investment · scope not declared (USD)
$140M
Subsidy Status
disbursing

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

AnnouncedSept 2020
FIDJan 2021
ConstructionOct 2021
Operational2023

Readiness Score

90/ 100
Mature

Weighted checklist of public info. Not a prediction of success.

Development

✓Final Investment Decision+15
✓EPC Contract signed+10
✓Permits obtained+8
✓Grid connection secured+7

Commercial

✓Binding offtake agreement+15
✓MOU / offtake letter of intent(implied)+5
✓Confirmed price / tariff+5
✓Applied to government program+5

Financing

✓Project finance / debt secured(implied)+10
✓Subsidy (disbursing)+10

Track Record

✓Developer has completed H2 project+5
✓Developer has completed RE project+3
✓Developer has energy experience+2