Energiepark Mainz

Construction✓ Source-checked

Mainzer Stadtwerke AG / Linde GmbH

Project Overview

Country
Germany
Region
Rheinland-Pfalz
Capacity
5 MW
Technology
PEM Electrolysis
Investment
—
Subsidy Status
—

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

Announced2025
FID—
Construction2025
Operational2027planned date

Readiness Score

50/ 100
Developing

Weighted checklist of public info. Not a prediction of success.

Development

✓Final Investment Decision(implied)+15
✓EPC Contract signed(implied)+10
✓Permits obtained(implied)+8
✓Grid connection secured(implied)+7

Commercial

✗Binding offtake agreement+15
✓MOU / offtake letter of intent(implied)+5
✗Confirmed price / tariff+5
✗Applied to government program+5

Financing

✗Project finance / debt secured+10
–Subsidy (not recorded)+0

Track Record

✓Developer has completed H2 project+5
✓Developer has completed RE project+3
✓Developer has energy experience+2