All Projects

Scores recomputed 4 days ago

Nazare Green Hydrogen Valley, phase 1

Pre-FID✓ Source-checked

REGA ENERGY (Reganazaré SA), consortium with Secil, Cimpor, BA Glass, Vidrala, Crisal, Águas do Centro Litoral and GGND

Project Overview

Country
Portugal
Region
Portugal
Capacity
40 MW
Technology
Other
Investment · scope not declared (EUR)
€100M

≈ $108M, converted at EUR_TO_USD = 1.08, fixed on 1 Jun 2026

Subsidy Status
—

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

Announced2022
FID—
Construction—
Operational2025planned date · already passed

Readiness Score

0/ 100
Early Stage

Weighted checklist of public info. Not a prediction of success.

Development

✗Final Investment Decision+15
✗EPC Contract signed+10
✗Permits obtained+8
✗Grid connection secured+7

Commercial

✗Binding offtake agreement+15
✗MOU / offtake letter of intent+5
✗Confirmed price / tariff+5
✗Applied to government program+5

Financing

✗Project finance / debt secured+10
–Subsidy (not recorded)+0

Track Record

✗Developer has completed H2 project+5
✗Developer has completed RE project+3
✗Developer has energy experience+2