Green hydrogen projects in Australia
The green hydrogen projects GaugeH2 tracks in Australia: 105 projects, each checked against a public source, with their status, technology and capacity.
- projects
- 105
- projects
- MW in the active pipeline
- 88,782
- MW in the active pipeline
- operational
- 12
- operational
- with FID or in construction
- 8
- with FID or in construction
Announced
11
Pre-FID
31
FID
1
Construction
7
Operational
12
Delayed
2
Suspended
18
Cancelled
23
projects
20%
18%
62%
- PEM (21)20%
- Alkaline (19)18%
- Other or not disclosed (65)62%
Largest projects in the active pipeline
| Project | Developer | MW | Status |
|---|---|---|---|
| Western Green Energy Hub, final phase | 46,175 | Pre-FID | |
| Evergreen Project | 7,000 | Announced | |
| Amp Energy project | 5,000 | Pre-FID | |
| Western Green Energy Hub Phase 1 | 3,809 | Pre-FID | |
| Collinsvile Energy hub - Han Ho | 3,742 | Pre-FID | |
| H2-hub Gladstone (Queensland) | 3,000 | Pre-FID | |
| Allied Green Ammonia Northern Territory project | 3,000 | Pre-FID | |
| Green Springs | 2,950 | Pre-FID | |
| Sun Brilliance West Australia Project, phase 2 and 3 | 1,900 | Announced | |
| Murchison, phase 2 | 1,500 | Announced |
The active pipeline excludes cancelled and suspended projects. Capacities are electrolyser capacities as announced by each project; projects without a published capacity do not add MW. Figures come live from the catalogue.