All Projects

Scores recomputed 4 days ago

European Energy / Engie 150 MW Danish Green Hydrogen

Announced✓ Source-checked

European Energy / Engie

Project Overview

Country
Denmark
Region
Aabenraa/Kassø
Capacity
150 MW
Technology
—
Investment
—
Subsidy Status
approved

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

AnnouncedJun 2026
FID—
Construction—
Operational2030planned date

Readiness Score

13/ 100
Early Stage

Weighted checklist of public info. Not a prediction of success.

Development

✗Final Investment Decision+15
✗EPC Contract signed+10
✗Permits obtained+8
✗Grid connection secured+7

Commercial

✗Binding offtake agreement+15
✗MOU / offtake letter of intent+5
✗Confirmed price / tariff+5
✓Applied to government program+5

Financing

✗Project finance / debt secured+10
✓Subsidy (approved)+5

Track Record

✗Developer has completed H2 project+5
✓Developer has completed RE project+3
✓Developer has energy experience+2