Hydrogen Energy Metallurgical Chemical Demonstration Zone, phase 2

FID✓ Source-checked

China Huadian / Inner Mongolia Huadian Huayang Hydrogen Technology

Project Overview

Country
China
Region
Inner Mongolia
Capacity
Not published
Technology
Alkaline Electrolysis
Investment
—
Subsidy Status
—

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

Announced—
FID2025
Construction2026planned date
Operational2027planned date

Readiness Score

33/ 100
Developing

Weighted checklist of public info. Not a prediction of success.

Development

✓Final Investment Decision(implied)+15
✓EPC Contract signed(implied)+10
✓Permits obtained(implied)+8
✗Grid connection secured+7

Commercial

✗Binding offtake agreement+15
✗MOU / offtake letter of intent+5
✗Confirmed price / tariff+5
✗Applied to government program+5

Financing

✗Project finance / debt secured+10
–Subsidy (not recorded)+0

Track Record

✗Developer has completed H2 project+5
✗Developer has completed RE project+3
✗Developer has energy experience+2