Indian Oil Corporation Green H2 Panipat

Construction✓ Source-checked

L&T Energy GreenTech Ltd (LTEG) — IOCL is off-taker under 25-yr BOO

Source: IEA Hydrogen Projects Database (September 2025)

Project Overview

Country
India
Region
Haryana
Capacity
118 MW
Technology
Alkaline Electrolysis
Investment · scope not declared (USD)
$600M
Subsidy Status
applied

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

AnnouncedDec 2022
FIDJul 2025
Construction—
OperationalDec 2027planned date

Readiness Score

57/ 100
Advanced

Weighted checklist of public info. Not a prediction of success.

Development

✓Final Investment Decision(implied)+15
✓EPC Contract signed(implied)+10
✓Permits obtained(implied)+8
✓Grid connection secured(implied)+7

Commercial

✓Binding offtake agreement+15
✓MOU / offtake letter of intent(implied)+5
✗Confirmed price / tariff+5
✗Applied to government program+5

Financing

✗Project finance / debt secured+10
✗Subsidy (applied)+0

Track Record

✗Developer has completed H2 project+5
✗Developer has completed RE project+3
✓Developer has energy experience+2