Port of Antwerp-Bruges AEM electrolyser

Operational✓ Source-checked

Power to Hydrogen (P2H2), Columbus, Ohio; concession of the Port of Antwerp-Bruges in NextGen Demo

Project Overview

Country
Belgium
Region
Vlaanderen
Capacity
0.5 MW
Technology
Other
Investment
—
Subsidy Status
—

Model this project

Opens the LCOH calculator prefilled from this row. The catalogue fills nine of the twenty-one inputs; the rest are platform defaults until you set them, and the report says which is which.

Open in LCOH calculator

Development Timeline

Announced—
FID—
Construction—
Operational2025

Status History

DateChangeReasonSource
19 Sept 2026construction → operationalThe article describes Power to Hydrogen (P2H2) beginning commercial green hydrogen production at the Port of Antwerp-Bruges using 250 kW AEM stacks. This matches the existing DB entry 'Port of Antwerp-Bruges AEM electrolyser' (ID: 0e3e4de2) which lists Power to Hydrogen (P2H2) as developer with 0.5 MW capacity and status 'construction'. The project has now moved to operational status.—

Readiness Score

70/ 100
Advanced

Weighted checklist of public info. Not a prediction of success.

Development

✓Final Investment Decision(implied)+15
✓EPC Contract signed(implied)+10
✓Permits obtained(implied)+8
✓Grid connection secured(implied)+7

Commercial

✓Binding offtake agreement(implied)+15
✓MOU / offtake letter of intent(implied)+5
✓Confirmed price / tariff(implied)+5
✗Applied to government program+5

Financing

✓Project finance / debt secured(implied)+10
–Subsidy (not recorded)+0

Track Record

✗Developer has completed H2 project+5
✗Developer has completed RE project+3
✗Developer has energy experience+2